Contractor:
(a) by obtaining copies of the Laws of the Country which are
relevant to the Contract but are not readily available, and
for the Contractor’s applications for any permits, licences or
approvals required by the Laws of the Country:
(i) which the Contractor is required to obtain under
Sub-Clause 1.13 [Compliance with Laws],
for the delivery of Goods, including clearance through
customs, and
for the export of Contractor’s Equipment when it is
removed from the Site. (b) (ii) (iii)
2.3 Employer’s personnel
The Employer shall be responsible for ensuring that the Employer’s Personnel and the Employer’s other contractors on the Site:
(a) co-operate with the Contractor’s efforts under Sub-Clause 4.6
[Co-operation],and
take actions similar to those which the Contractor is required to
take under sub-paragraphs (a), (b) and (c) of Sub-Clause 4.8
[Safety Procedures] and under Sub-Clause 4.18 [protection of
the Environment]. (b)
2.4 Employer’s Financial Arrangements
The Employer shall submit, within 28 days after receiving any request from the Contractor, reasonable evidence that financial arrangements have been made and are being maintained which will enable the Employer to pay the Contract Price (as estimated at that time) in accordance with Clause 14 [Contract Price and Payment]. If the Employer intends to make any material change to his financial arrangements, the Employer shall give notice to the Contractor with detailed particulars.
2.5 Employer’s Claims
If the Employer considers himself to be entitled to any payment under any Clause of these Conditions or otherwise in connection with the Contract, and/or to any extension of the Defects Notification Period, he