地下室设计深基坑中英文对照外文翻译文献(2)

来源:网络收集 时间:2025-09-24 下载这篇文档 手机版
说明:文章内容仅供预览,部分内容可能不全,需要完整文档或者需要复制内容,请下载word后使用。下载word有问题请添加微信号:xuecool-com或QQ:370150219 处理(尽可能给您提供完整文档),感谢您的支持与谅解。点击这里给我发消息

than the diameter of piles. Spacing is decided based on type of soil and level of design moments but it should not be too large, otherwise pieces of lumps etc. drop and extra precautions are needed. Cohesive soils or soils having some cohesion are suitable. No water table should be present. Acceptable amount of water is collected at the base and pumped out. Common diameters are 0.60, 0.80, 1.00 m. Waling beams (usually called ?breasting beams ) are Tangent piles with grouting in between are used when secant piling or diaphragm walling equipment is not available (i.e. in cases where ground water exists). Poor workmanship creates significant problems.

Secant bored pile walls are formed by keeping spacing of piles less than diameter (S

There is also need for place for the plant. It may be constructed “hard-hard”as well as “soft-hard”. “S oft”concrete pile contains low cement content

and some bentonite. Primary unreinforced piles are constructed first and then

reinforced secondary piles are formed by cutting the primary piles. Pile

construction methods may vary in different countries for all type of pile walls like full casing support, bentonite support, continuous flight auger (CFA) etc.

mostly reinforced concrete but sheet pile sections or steel beams are also used.

Diaphr agm Walls

Diaphragm wall provides structural support and water tightness. It is a classical technique for many deep excavation projects, large civil engineering

works, underground car parks, metro pits etc. especially under water table. These reinforced concrete diaphragm (continuous) walls are also called slurry trench walls due to the reference given to the construction technique where

excavation of wall is made possible by filling and keeping the wall cavity full with bentonite-water mixture during excavation to prevent collapse of the excavated vertical surfaces. Wall thickness varies between 0.50 m and 1.50 m.

The wall is constructed panel by panel in full depth.Panel lengths are 2 m to 10 m. Short lengths (2-2.5 m) are selected in unstable soils or under very high surcharges. Nowadays depth of panels water stops exceeded 100 m,

excavation depths exceeded 50 m. Different panel shapes other than the conventional straight section like T, L, H, Y, + are possible to form and used for special purposes. Panel excavation is made by cable or kelly supported

buckets and by a recent design called ?cutter or ?hydrofraise which is a pair of hydraulically operated rotating disks provided with hard cutting tools. Excavation in rock is possible. Slurry wall technique is a specialized

technique and apart from the bucket or the frame carrying the cutter equipment like crawler crane, pumps, tanks, desanding equipment, air lifts, screens, cyclones, silos, mixers, extractor are needed. Tremie concrete is

placed in the slurry starting from the bottom after lowering reinforcement

cages. Joint between the panels is a significant detail in water bearing soils and steel pipe, H-beam or water stops are used.

R einforced C oncrete R eta ining Walls Excavation in Stages It is a common type of staged excavation wall usually supported by ground anchors. Soils with some cohesion are suitable because each stage is first excavated before formwork and concrete placement. No water table or appreciable amount of water should be present. Sometimes micropile support is given if required due to expected cave-ins.

Soil Nail Walls

Similar to the method above excavation is made step by step (1.5 to 2 m high). Shotcrete is common for facing and wiremesh is used. Soft facing is also possible making use of geotextiles. Hole is drilled, ordinary steel bars are lowered, and grout is placed without any pressure. Soil should be somewhat cohesive and no water table or significant water flow should be present.

Coffer dams

Cofferdam is a temporary earth retaining structure to be able to make excavation for construction activities. It is usually preferred in the coastal and

sea environment like bridge piers and abutments in rivers, lakes etc., wharves, quay walls, docks, break waters and other structures for shore protection,

large waterfront structures such as pump houses, subjected to heavy vertical and horizontal loads. Sheet piling is commonly used in various forms other

than conventional walls like circular cellular bodies or double walls connected inside and filled with sand. Stability is maintained by sheeting driven deeper than base, sand body between sheeting and inside tie rods. Earth embankments and concrete bodies are also used. Contiguous, tangent, secant piles or diaphragm walls are constructed in circular shapes, and no internal bracing or anchoring is used to form a cofferdam. Reinforced concrete waling beams support by arching. Shafts are also made with this method. Large excavations or project details may require additional lateral support.

J et Grout and Deep M ixed Walls

Retaining walls are made by single to triple row of jet grout columns or deep mixed columns. There is a soil mixed wall(SMW) technique specially developed for wall construction where H sections are used for reinforcement. Single reinforcing bar is placed in the central hole opened for jet grout columns. Anchors, nails or struts may be used for support.

Top Down Constr uction

Retaining structure (generally diaphragm wall) is designed and constructed as permanent load bearing walls of basement. Piles or barettes are similarly placed to complete the structural frame. Top slab is cast at the ground surface level, and excavation is made under the slab by smaller sized

excavators and continued down forming basement slabs at each level. There are special connection details. Top down method is preferred in highly

populated city centers where horizontal and vertical displacements are very critical, and anchors and struts are very difficult to use due to complex underground facilities and lifeline structures and site operations are difficult to perform.

Pa r tia l Excavation or Island M ethod

It is possible to give strut support to retaining walls at a later stage after constructing central sections of a building in large size excavations. Core of the structure is built at the central part making sloped excavations at peripheral areas and then the core frame is used to give support to walls (Figure 1.9). It may be more practical and construction time may be less compared to conventional braced system. This method may not be suitable in soft and weak soils due to stability and deformation problems during sloped excavations.

2. EARTH PR ESSUR ES ON IN-SITU R ETAINING WAL L S

Introduction

Earth pressures on in-situ retaining walls are rather different than those on ordinary retaining walls due to the supporting elements. Free displacement

of walls are not allowed. Type of support affects the distribution of earth pressure. Strut loads were measured in strutted excavations in many countries

in the past, and recommendations were given. Ground anchor technology is relatively new, and data on instrumented anchored walls for total lateral

百度搜索“70edu”或“70教育网”即可找到本站免费阅读全部范文。收藏本站方便下次阅读,70教育网,提供经典综合文库地下室设计深基坑中英文对照外文翻译文献(2)在线全文阅读。

地下室设计深基坑中英文对照外文翻译文献(2).doc 将本文的Word文档下载到电脑,方便复制、编辑、收藏和打印 下载失败或者文档不完整,请联系客服人员解决!
本文链接:https://www.70edu.com/wenku/410585.html(转载请注明文章来源)
Copyright © 2020-2025 70教育网 版权所有
声明 :本网站尊重并保护知识产权,根据《信息网络传播权保护条例》,如果我们转载的作品侵犯了您的权利,请在一个月内通知我们,我们会及时删除。
客服QQ:370150219 邮箱:370150219@qq.com
苏ICP备16052595号-17
Top
× 游客快捷下载通道(下载后可以自由复制和排版)
单篇付费下载
限时特价:7 元/份 原价:20元
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:xuecool-com QQ:370150219