3. SETTING UP AN EFFICIENT CONTROL SYSTEM

For the purpose of achieving cost target, the manager need to set up an efficient management framework including: reporting structure, assessing progress, and communication system. The employees' responsibility and authority need to be defined in the reporting structure. The formal and informal assessing progress can help getting a general perspective between reality and target. It is significant to help identify what is the risk and should be monitored and controlled. Project success is strongly linked to communication. The efficient communication system benefit for teamwork and facilitate problem solving ( Diallo and Thuillier, 2005 ).

4. COST MONITOR AND CONTROL

4.1 Ranking the priority of monitoring

In construction phase, many activities are carried out based on the original plan. It is need to know what kind of activities or things are most likely to lead the project delay and disruption. Therefore, the first step is ranking the priority of the activities. Because the duration of a project is determined by the total time of activities on critical path, any delay in an activity on the critical path will cause a delay in the completion date for the project (Ackermann Eden, Howick and Williams,2000,p295). Therefore, the activities on critical path should firstly to be monitored and controlled. Secondly, monitoring the activities with no free float remaining, a delay in any activity with no free float will delay some subsequent activity inevitably. These subsequent delays will discomfit the resource schedule significantly. Some resources are unavailable because they are committed elsewhere. Thirdly, monitoring the activities with less than a specified float, because if an activity has very little float, it might use up the time before control decision is made once such an activities has a variance with the target. Fourthly, managers should monitor high risky activities. High risky activities are most likely to overspend. Fifthly, managers should monitor the activities using critical resource. Some resource is critical because they are very expensive or limited (Cotterell and Hughes, 1995).

4.2Methods of cost control

The main cost of a project includes staff cost, material cost and delay cost. To control these cost, managers should first set up a cost control system to: a) Allocate responsibilities for administration and analysis of financial data

百度搜索“70edu”或“70教育网”即可找到本站免费阅读全部范文。收藏本站方便下次阅读,70教育网,提供经典教育范文成本管理外文文献翻译(2)在线全文阅读。

成本管理外文文献翻译(2).doc 将本文的Word文档下载到电脑,方便复制、编辑、收藏和打印 下载失败或者文档不完整,请联系客服人员解决!
本文链接:https://www.70edu.com/fanwen/1183652.html(转载请注明文章来源)

相关推荐:

Copyright © 2020-2025 70教育网 版权所有
声明 :本网站尊重并保护知识产权,根据《信息网络传播权保护条例》,如果我们转载的作品侵犯了您的权利,请在一个月内通知我们,我们会及时删除。
客服QQ:370150219 邮箱:370150219@qq.com
苏ICP备16052595号-17
Top
× 游客快捷下载通道(下载后可以自由复制和排版)
单篇付费下载
限时特价:7 元/份 原价:20元
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
VIP包月下载
特价:29 元/月 原价:99元
低至 0.3 元/份 每月下载150
全站内容免费自由复制
注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信:xuecool-com QQ:370150219